UPSC MainsMANAGEMENT-PAPER-II201710 Marks
Q11.

Calculate the activity slacks and determine the critical path using the expected activity times.

How to Approach

This question requires applying project management techniques – specifically, calculating activity slacks and identifying the critical path. The approach involves first understanding the concept of expected activity times (typically using the PERT method – Program Evaluation and Review Technique). Then, calculate early start (ES), early finish (EF), late start (LS), and late finish (LF) times for each activity. Slack is calculated as LF-EF or LS-ES. The critical path consists of activities with zero slack. A clear tabular representation of the calculations is crucial for a well-structured answer.

Model Answer

0 min read

Introduction

Project management is a crucial aspect of efficient resource allocation and timely completion of tasks, particularly in large-scale endeavors. The Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) are essential tools used to schedule, organize, and control projects. These techniques help identify the sequence of activities that determine the shortest possible duration of a project. Calculating activity slacks and determining the critical path are fundamental steps in these methodologies, enabling project managers to focus on activities that directly impact project completion time. This answer will demonstrate the calculation of activity slacks and the identification of the critical path, assuming the availability of expected activity times.

Understanding Expected Activity Times and Network Diagram

Before calculating slacks and the critical path, we need the project network diagram and the expected activity times. Since the question doesn't provide this, we will *assume* a simplified project with the following activities and expected times (in days):

Activity Predecessor Expected Time (days)
A - 4
B A 5
C A 6
D B 7
E C 3
F D, E 2

This table represents a project where activity A must be completed before B and C can start. Activity D depends on B, E on C, and finally, F depends on both D and E. We will now proceed with the calculations.

Calculating Early Start (ES) and Early Finish (EF)

The ES of an activity is the earliest time it can start, given the completion of its predecessors. The EF is the ES plus the activity duration. We start from the beginning of the project (time 0).

Activity Duration ES EF
A 4 0 4
B 5 4 9
C 6 4 10
D 7 9 16
E 3 10 13
F 2 16 18

Calculating Late Start (LS) and Late Finish (LF)

The LF is the latest time an activity can finish without delaying the project. The LS is the LF minus the activity duration. We start from the end of the project (time 18) and work backward.

Activity Duration LF LS
F 2 18 16
D 7 16 9
E 3 16 13
B 5 9 4
C 6 10 4
A 4 4 0

Calculating Slack

Slack is the amount of time an activity can be delayed without delaying the project. It is calculated as LF - EF or LS - ES.

Activity EF LF Slack (LF-EF)
A 4 4 0
B 9 9 0
C 10 10 0
D 16 16 0
E 13 16 3
F 18 18 0

Identifying the Critical Path

The critical path consists of activities with zero slack. In this example, the critical path is A -> B -> D -> F. These activities must be completed on time to ensure the project finishes on schedule. Any delay in these activities will directly delay the entire project.

Conclusion

In conclusion, calculating activity slacks and identifying the critical path are vital for effective project management. By determining the activities with zero slack, project managers can prioritize resources and focus on ensuring timely completion of these critical tasks. The example demonstrates a simplified project, but the principles apply to complex projects as well. Utilizing tools like CPM and PERT, along with accurate time estimations, significantly increases the likelihood of project success.

Answer Length

This is a comprehensive model answer for learning purposes and may exceed the word limit. In the exam, always adhere to the prescribed word count.

Additional Resources

Key Definitions

Critical Path
The longest sequence of activities in a project plan which must be completed on time for the project to complete on schedule. It determines the shortest possible duration of the project.
Slack (or Float)
The amount of time an activity can be delayed without delaying the overall project completion date or violating a schedule constraint.

Key Statistics

According to a 2013 study by the Project Management Institute (PMI), only 54% of IT projects are completed on time and within budget.

Source: Project Management Institute (PMI), 2013

A study by Standish Group found that approximately 30% of all IT projects are canceled before they ever get completed, often due to poor planning and project management.

Source: Standish Group, Chaos Report (Knowledge cutoff 2023)

Examples

Construction of the Burj Khalifa

The construction of the Burj Khalifa in Dubai heavily relied on CPM and PERT techniques to manage the complex schedule and numerous activities involved in building the world's tallest structure. Careful monitoring of the critical path was essential to avoid delays.

Frequently Asked Questions

What happens if an activity on the critical path is delayed?

If an activity on the critical path is delayed, the entire project completion date is delayed by the same amount of time. This is because these activities have zero slack, meaning there's no buffer for delays.