UPSC MainsGeneral Studies Paper IGeographyPractice question

Opportunities and Challenges of Ken-Betwa Link Project

The Ken-Betwa link project reflects both the opportunities and challenges of river linking in India. Discuss.

Discuss~250 words2 min readmedium
Attempt it first, timed · optional

Write the answer on paper, as in the exam. Start the timer, keep to the word target.

00:00/ 11 min · 250 words

Done writing? Photograph the sheet and see how it scores against this model answer, with feedback on what to fix.

Upload your answer sheet

How to approach

Begin by introducing the Ken-Betwa Link Project (KBLP) as India's pioneer river interlinking initiative under the National Perspective Plan. Analyse the socio-economic and regional development opportunities it brings to Bundelkhand, followed by an examination of the ecological, hydrological, and rehabilitation challenges. Conclude with a balanced way forward focusing on comprehensive landscape management and decentralized water conservation.

Model answer

395 words

Introduction

The Ken-Betwa Link Project (KBLP), with an approved outlay of ₹44,605 crore, is India's pioneer river interlinking initiative under the National Perspective Plan. Aimed at transferring surplus water from the Ken basin in Madhya Pradesh to the water-deficit Betwa basin in Uttar Pradesh, it serves as a critical test case demonstrating both the socio-economic promise and the environmental trade-offs of large-scale river interlinking.

Opportunities: Socio-Economic Transformations

The interlinking of the Ken and Betwa rivers offers significant potential to alleviate distress in one of India's most drought-vulnerable regions:

  • Water and Food Security: The project is designed to provide annual irrigation to 10.62 lakh hectares of agricultural land and ensure drinking water supply to over 62 lakh people across the drought-prone Bundelkhand region, mitigating recurrent agricultural distress and seasonal distress migration.
  • Clean Energy Generation: The multi-purpose project will contribute to renewable energy generation by producing 103 MW of hydroelectric power and 27 MW of solar power.
  • Strengthening Cooperative Federalism: The 2021 Tripartite Memorandum of Understanding signed between the Union Government, Madhya Pradesh, and Uttar Pradesh resolved long-standing interstate riparian disputes, establishing a cooperative institutional framework for inter-basin water management.

Challenges: Ecological, Hydrological, and Social Costs

Despite its developmental promises, the project encounters multifaceted challenges spanning ecology, hydrology, and community displacement:

  • Ecological Degradation in Panna Tiger Reserve: The construction of the Daudhan Dam will submerge approximately 5,258 hectares of forest land within the core habitat of Panna Tiger Reserve (PTR), jeopardizing tiger corridors, Ken Gharial Sanctuary habitats, and nesting sites of endangered vulture species.
  • Displacement and Rehabilitation: The project necessitates the relocation of nearly 6,000 families across about 10 villages, requiring rigorous compliance with the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013, as well as informed Gram Sabha consent under the Forest Rights Act (FRA), 2006.
  • Hydrological Viability and Climate Variability: Interlinking models depend heavily on the static categorization of river basins into 'surplus' and 'deficit'. The Ken is predominantly non-perennial, and changing monsoon patterns driven by climate change could lead to reduced lean-season flows, affecting the sustainability of inter-basin transfers.

Conclusion

To harmonize developmental imperatives with conservation, the execution of the Ken-Betwa Link Project must strictly integrate the Integrated Landscape Management Plan (ILMP) for the Greater Panna Landscape. Combining inter-basin transfers with decentralized water conservation measures like farm ponds and check dams will ensure long-term, sustainable water security for Bundelkhand.

Key facts to remember

statistic

The Ken-Betwa Link Project is targeted to irrigate 10.62 lakh hectares annually and provide drinking water to 62 lakh individuals in the Bundelkhand region.

Ministry of Jal Shakti
statistic

The construction of the Daudhan Dam will result in the submergence of approximately 5,258 hectares of forest area inside the Panna Tiger Reserve core.

National Tiger Conservation Authority
scheme
Integrated Landscape Management Plan (ILMP)

A comprehensive conservation framework prepared by the Wildlife Institute of India to offset biodiversity loss and maintain wildlife connectivity across the Greater Panna Landscape.

Frequently asked questions

What makes the Ken-Betwa Link Project significant among Indian river interlinking projects?

The Ken-Betwa Link Project is India's first river interlinking project implemented under the National Perspective Plan, serving as an operational model for future inter-basin water transfers across the country.